The 1855 Place project is almost finished!
The project was broken down into two phases in order to maintain event parking during construction. Phase 1 was completed in 2016 and included family housing and a new parking structure. This structure and the adjacent surface lot provide an additional 2,075 spaces for visitor and event parking.
Phase 2 of the project is currently underway and is projected to finish by summer 2017. This phase of the project includes a mixed use office building and single student housing. The office building will be 102,000 square feet and will include RHS offices, the intercollegiate athletic office and retail space. RHS and Intercollegiate Athletics staff will move into their new offices between September 2017 and January 2018.
Pedestrian detours around the site work will continue through the project duration. If you would like more information on detours, you can access a detailed map on the Infrastructure and Planning Facilities website.
To keep up to date on this and other construction projects, visit the IPF website.